28 March 2024 - Announcement of the launch of a new Share Buy-Back program 22 March 2024 - FY 2024 Half-year results: EBITDA margin of 62%, above the Group’s 2026 target, Confirmed financial strength to support the Group’s growth drivers 8 March 2024 - Hydrogen development strategy in Lorraine 1 March 2024 - Completion of the acquisition of a majority stake in Greenstat ASA, a leading green energy player in Norway 24 January 2024 - Revenue of €17.6 million in H1 2024, +16% Q2 2024 revenue growth compared to Q1 2024, Strong developments confirmed for 2024 16 January 2024 - FDE set to acquire a controlling stake in Greenstat ASA in Norway 9 January 2024 - Half-year statement of the liquidity contract 7 December 2023 - La Française de l’Énergie (FDE) improves its Gaïa Research rating in 2023
Bourse FDE.PA 34.80 EUR0.29%

News

Framework agreement signed with 2G Energietechnik GmbH to speed up the installation of green electricity production units

5 August 2020

Forbach, France, August 4th, 2020 – La Française de l’Énergie (Euronext: LFDE – ISIN: FR0013030152) leader in industrial ecology, is delighted to announce the signature of a 3-year framework agreement with the German company 2G Energietechnik GmbH for the supply of cogeneration units dedicated to the production of green electricity from mine gas in France and Belgium.

Thanks to this partnership with 2G, a leading manufacturer of decentralized energy production systems in Europe, La Française de l’Énergie benefits from competitive commercial conditions with  a guaranteed fixed price for the duration of the contract and major logistic related advantages such as free storage of engines for several months and dedicated production lines for major orders. These improved terms and conditions will allow the Group to reinforce its capacity of development and improve the profitability of its future production sites.

A framework agreement covering 25 new cogeneration units

Covering the full scope of the Group’s needs (engine, cogeneration kits and soundproofed containers), this agreement also secures the supply of cogeneration units for the deployment of new sites, of which 37.5 MW are scheduled in Hauts-de-France and Wallonia.

To this end, the delivery schedule of 7 cogeneration units (10.5 MW) has been confirmed at the agreed terms and conditions, for an installation planned over the next 12 months in Béthune, Avion and Anderlues. The 18 additional cogeneration units (27 MW) will be installed on the new sites in Hauts-de-France as soon as the approvals from the administration will be delivered.

Benefiting from an enhanced execution capacity and a secure development plan, La Française de l’Énergie confirms its ambition to actively participate in Europe’s ecological and energy transition through the launch of new production sites of green energy.